Stages 11 & 12 Update

While we wait for Nelson City Council to issue both the 223 and 224 certificate (223 being acknowledgement by NCC that all work on stages[…]

Stages 7 & 9 Update

Sorry, it’s been over a month since I updated progress. While stages 7 & 9 just inside the gates ( gates now gone of course[…]

Asphalt Complete – January 2025

Wow, two posts in one week. Following on from yesterday’s photos the Asphalt has now been completed right to the gates at the entry to[…]

Asphalting Underway – January 2025

Everything is taking shape here in Marsden Park with the road asphalting well and truly underway. Contact our preferred home builders today to secure one[…]

Sprig & Fern progress November 2024

See below for some new progress images of the Sprig & Fern Tavern at Marsden Park

Stages 7 & 9 nearing completion

Well we are edging towards the completion of stages 7 & 9 in Marsden Park subdivision. Last of the power & comms installed, footpaths continuing[…]

Laneways and kerbs update October 2024

More progress. Ching Contracting now have both laneways ready to seal, and first of the kerb going in on the Homestead Drive extension upwards from[…]

Construction Update 18/10/2024

Well, despite a bit more rain, the Ching Contracting team onsite are heading into the home straight, on the current stage. It’s been 8 months[…]

Sprig & Fern progressing, infrastructure updates

The new Sprig & Fern building in Marsden Valley is progressing well. Up behind that it’s all pipes and wires. Ching Contracting are well underway[…]